Title:
Field Inspection and Testing of Concrete
Author(s):
G.H. Bayles
Publication:
Journal Proceedings
Volume:
8
Issue:
3
Appears on pages(s):
501-521
Keywords:
none
DOI:
10.14359/16173
Date:
3/1/1912
Abstract:
In the spring of 1910 we were commissioned to design and superintend the construction of a warehouse 100 x 210 ft., 4 stories high, in the Borough of Brooklyn, New York, for the New York Dock Company. The use of reinforced concrete was recommended and adopted, but from experience and knowledge of the many criticisms of this material and the considerable number of failures in its use, it was decided that very careful inspection should be maintained.