Expediting Construction On The Pennsylvania Turnpike
Author(s):
H. Hershey Miller
Publication:
Journal Proceedings
Volume:
37
Issue:
Appears on pages(s):
349-360
Keywords:
none
DOI:
10.14359/8557
Date:
2/1/1941
Abstract:
Engineers of Turnpike Commission were confronted with t he task of p-lacing more than 4 million sq yd of 9-in. unrform reinforced concrete pavement in 2 1/2 The 1 2 ft pavement consisted of four lanes, each lane 160 miles long. The analysis of the problem and the steps taken to solve it are the subject matter of this paper.