Title:
Quality Control and Application New Melones Project
Author(s):
Leland A. Case
Publication:
Symposium Paper
Volume:
45
Issue:
Appears on pages(s):
235-245
Keywords:
DOI:
10.14359/17949
Date:
1/1/1974
Abstract:
The New Melones Projet sucessfully used shotcrete, in conjunction with 10' and 15' rock bolts, as a primary tunnel support method. The New Melones Diversion Tunnel was 3,800 feet long with a horseshoe cross-section nominally 30' wide by 18' to 24' below spring line.