International Concrete Abstracts Portal

International Concrete Abstracts Portal

The International Concrete Abstracts Portal is an ACI led collaboration with leading technical organizations from within the international concrete industry and offers the most comprehensive collection of published concrete abstracts.

Showing 1-5 of 23 Abstracts search results

Document: 

SP120-06

Date: 

June 1, 1990

Author(s):

Pham Xuan Thao

Publication:

Symposium Papers

Volume:

120

Abstract:

The use of tendons placed outside the concrete for the longitudinal prestressing of bridge decks is particularly well suited to the triangulated trusses that have now proven effective. Experience acquired first on the Tehran Stadium roofing (internal tendons) and then on the externally prestressed Bubiyan Bridge in Kuwait has highlighted the numerous advantages to be derived from the latter system. The technology has, therefore, been used again, with external tendons, in the construction of the Sylans and Glacieres viaducts located along the Macon-Geneva-Mont Blanc highway in France, on behalf of the Societe des Autoroutes Paris Rhin-Rhone. The two viaducts have a total length of 1500 m. Each consists of two parallel decks, 10.75 m wide. Typical spans are 60 m long. The deck is precast in forms as a series of 4.66 m long elements and erected by sequential cantilevering using a launching girder.

DOI:

10.14359/3424


Document: 

SP120-07

Date: 

June 1, 1990

Author(s):

Alan Matejowsky

Publication:

Symposium Papers

Volume:

120

Abstract:

The state of Texas is involved in two projects that use precast concrete segmental erection methods with external post-tensioning tendons. Design and construction features of these projects, along with construction problems related to external tendons, are described. The future of segmental construction and use of external tendons in Texas are discussed.

DOI:

10.14359/3428


Document: 

SP120-08

Date: 

June 1, 1990

Author(s):

G. Causse

Publication:

Symposium Papers

Volume:

120

Abstract:

The bridge that links Re Island and the mainland was completed in April, 1988. It crosses a 3000 m wide sea channel that separates the island from the town of La Rochelle, on the west coast of France. The deck of the bridge is a concrete box girder built by the balanced cantilever method with precast segments. The prestressing tendons are partly inside the concrete and partly external.

DOI:

10.14359/3433


Document: 

SP120-11

Date: 

June 1, 1990

Author(s):

Andrew E. N. Osborn and H. Kent Preston

Publication:

Symposium Papers

Volume:

120

Abstract:

Over 600 bridges composed of adjacent prestressed concrete box beams were built in the early 1950s in Pennsylvania. The box beams were placed side by side and had an asphalt wearing course on top. Span lengths ranged form 30 to 60 ft. Their design was very conservative by today's standards. The concretes used in these bridges have high chloride contents; water leaks down through the joint between box units and the strands often have inadequate cover. Thus, it is not surprising that many of the box beams are deteriorating due to corrosion of their prestressing strands. This project was directed toward developing economical repair schemes for these bridges. The literature survey did not reveal any schemes specifically applicable to adjacent box beams. Two external reinforcement repair schemes were developed and trial installations were made on a bridge near York, Pa. Both schemes included the removal of deteriorated concrete, placement of external reinforcement beneath the beam, and application of shotcrete to the soffit of the beam. In Scheme 1, the external reinforcement consisted of epoxy-coated reinforcing bars. This repair method restored ultimate flexural capacity but did not restore lost prestress. It was the least costly of the two methods. In Scheme 2, post-tensioned, epoxy-coated strand was used. This restored the full ultimate flexural capacity and most of the lost prestress. Difficulties were encountered in installing anchors for the post-tensioned system, but its performance was good. The bridge was tested after repair. The external reinforcements were found to be fully composite with the original beams. The tests also revealed the lateral distribution of wheel loads. In spite of the poor condition of the bridge, the wheel loads were well distributed laterally, leading to a structure that was stronger and stiffer than expected.

DOI:

10.14359/3437


Document: 

SP120-10

Date: 

June 1, 1990

Author(s):

F. Wayne Klaiber, Kenneth F. Dunker and W. W. Sanders, Jr.

Publication:

Symposium Papers

Volume:

120

Abstract:

Approximately 40 percent of the bridges in the United States are classified as deficient and in need of rehabilitation or replacement. Of these bridges, many are classified as deficient because their load-carrying capacity is inadequate for today's increased traffic. This insufficient load-carrying capacity has resulted from poor maintenance, increase in legal load limits, deck overlays, changes in design specifications, and other factors. In response to the need for a simple, efficient procedure for strengthening existing bridges, the authors have been investigating the use of post-tensioning. They have investigated its use on simple span bridges as well as continuous span bridges. Various post-tensioning schemes have been tested on laboratory models and actual bridges. The paper briefly reviews the post-tensioning research that has been completed by the authors in the past few years. This work indicates that post-tensioning is a viable, economical technique for flexural strengthening of steel-beam composite-concrete deck bridges.

DOI:

10.14359/3255


12345

Results Per Page 




Edit Module Settings to define Page Content Reviewer