Historical entry from ACI 116R-00, used prior to revision posted on July 1, 2008:
joint, cold — a joint or discontinuity resulting from a delay in placement of sufficient duration to preclude intermingling and bonding of the material in two successive lifts of concrete, mortar, or the like.
Back to ACI Concrete Terminology