|
|
Emergency Construction Joint Procedures |
| |
|
|
Q. While the contractor was placing a trench footing, the
concrete supply was interrupted, creating an unexpected
cold joint. The footing is 2 ft (0.6 m) wide, 4 ft (1.2 m) deep,
and 40 ft (12 m) long with 10 longitudinal reinforcing bars
(three top and bottom and two on each side) enclosed by
stirrups. The cold joint is not at a uniform depth. It’s about 1 ft
(0.3 m) below the plan elevation for 20 ft (6 m), then slopes
all the way to the bottom of the footing at the 40 ft (12 m)
mark. What should have been done when it was apparent that
an emergency construction joint was needed?
A. Emergency construction joints are sometimes
needed when unexpected work stoppages occur.
Documents in the ACI Manual of Concrete Practice don’t
mention or distinguish between procedures for emergency
or planned construction joints in structures other than
pavements. Two ACI documents briefly discuss preparation
of cold-joint surfaces prior to subsequent concrete
placements that are in contact with the surfaces. Section 3.5.7
of ACI 336.1-01, “Specification for the Construction of
Drilled Piers,”1 directs the contractor to:
“Place concrete in pier in one continuous operation,
unless otherwise directed by the Owner’s Representative-Geotechnical Engineer. Level, roughen, and clean the
surface of construction joints to the satisfaction of the
Owner’s Representative-Geotechnical Engineer before
recommencement of concrete placement. Provide
reinforcing dowels or shear key when directed by the
Owner’s Representative-Geotechnical Engineer.”1
Section 7.7.5 of ACI 309R-05, “Guide for Consolidation
of Concrete,”2 discusses cold joints as follows:
“Delays in concreting can result in cold joints. To avoid
cold joints, placing should be resumed substantially
before the time of initial set. For unusually long delays
during concreting, the concrete should be kept live by
periodically revibrating it. Concrete should be vibrated at
approximately 15 minute intervals or less, depending upon
job conditions. Concrete should not be overvibrated to
the point of causing segregation. Furthermore, should the
concrete approach time of initial setting, vibration should
be discontinued and the concrete should be allowed to
harden. A cold joint will result, and suitable surface
preparation measures should be applied.”2
If design professionals are on site or can be contacted,
they should make decisions regarding emergency
construction joints. The drilled piers document, for
instance, gives responsibility for discontinuing concrete
placement to the Owner’s Representative-Geotechnical
Engineer. We found some further guidance on this subject in
a section on bridge construction from the Illinois Department
of Transportation Construction Manual.3 The manual advises that construction joints in bridge superstructures should
be avoided at locations other than those shown on the
plans. It also states, however, that occasional equipment
breakdowns or sudden storms may make emergency
construction joints necessary. While the manual lists
preferred locations for emergency construction joints
in simple and continuous spans, it also states that
construction joints are permissible at other locations
if necessary in cases of a real emergency. It cautions,
however, to use sound judgment when making an emergency
construction joint and instructs field engineers to consult
their supervising engineer before granting permission to make a construction joint that is not of an emergency nature.
More detailed instructions for
emergency construction joints may be included in the specifications
for the project and may include
provisions requiring some or all of
the following:
Reinforcing bar dowels fully
developed on both sides of
the cold joint when the joint
is not perpendicular to the
primary reinforcing;
Thorough cleaning of the joint
face prior to placing additional
concrete;
Sandblasting to expose coarse
aggregate; and
Bedding grout worked into the
surface of the joint immediately
prior to placing additional concrete.
To summarize, in the absence of
specific instructions in the contract
documents, the design professional
should preferably make decisions
regarding the procedures to be
followed when an emergency
construction joint is needed. If the
design professional can’t be contacted
and immediate action is needed, the
contractor may have to bulkhead off
the placement and possibly install
reinforcing bars normal to the
construction joint surface. For the
trench footing you mentioned, the
bulkhead would usually be installed
with a vertical form normal to the
direction of the reinforcing steel.
The trench would then be filled to
the full depth of the footing. The
hardened concrete surface at the
bulkhead would then be prepared
following normal practice for
construction joints as directed by
the design professional.
References
- ACI Committee 336, “Specification for the
Construction of Drilled Piers (ACI 336.1-01),”
American Concrete Institute, Farmington Hills,
MI, 2001, p. 7.
- ACI Committee 309, “Guide for
Consolidation of Concrete (ACI 309R-05),”
American Concrete Institute, Farmington
Hills, MI, 2005, p. 19.
- Construction Manual, Illinois Department
of Transportation, Jan. 2006, Section 500,
pp. 7-8.
Purchase ACI documents at the ACI Bookstore
Posted 11/29/07.
Disclaimer: Questions in this column were asked by users of ACI documents and have been answered by ACI staff or by a member or members of ACI technical committees. The answers do not represent the official position of an ACI committee. Only a published committee document represents the formal consensus of the committee and the Institute. |
|
| |
Was this answer useful?
 |
|
 |
|